Harbour Island is a gated community of townhouses and mid-rise condo buildings on the bayside of 14th Street in Ocean City, Maryland. Amenities include tennis courts, swimming pool, boat slips, tot lot, real estate office, fuel dock, boardwalk, and the Reel Inn Restaurant and Dock Bar. The community is home of the White Marlin Open fishing tournament held the first full week of August each year.

L BUILDING ELEVATOR INFO
3/27/2020 Report from elevator crew: "T
hey will not be finished with L until towards end of next week. I will be able to give you a more approximate start date for M when they get closer to finishing up.Upon beginning this job, they did notice additional concrete work needed which is taking them longer than anticipated. We will just be covering this under our original proposal without a change order. I just wanted you to be aware since they will need an extra couple of days."
3/24/2020 Elevator crew yesterday measured old sills. The crew (2) is onsite today to remove the old sills, etc.
Work should be complete in approximately 6 days.


K BUILDING ELEVATOR UPDATES
03/27/2020
The job supervisor reports that the "controller, pump unit, car frame, platform, roller guides are all 100% complete.  In the next 2 weeks the new door equipment, sills, angles, hoistway duct and wiring  will be complete."
   

03/21/2020
Delaware Elevator announced that the project is ahead of schedule!
03/16/2020
Update from Delaware Elevator: So far demo is 100% complete, the new jack is set, running on construction mode, and the sling has been built. The project also continues to remain on schedule. Our crew’s schedules thus far have not been effected by the Coronavirus outbreak. Should anything change, we will certainly notify all.

03/06/2020
The hydraulic cylinder has been replaced. Work is now being done in the elevator machine room.

02/27/2020
An owner asked why workers are not working on the new elevator daily. Here is the information that was gathered from those involved with the project.
•The contract with Delaware does not stipulate days of the week to complete the project. The signed contract focuses on the completion date of May 1, 2020.
•Delaware’s crews often work 10-12 hours a day so they are usually not onsite 5 days per week.
•Due to the amount of elevator/renovation projects going on right before the summer season, the technicians have to work very rigorous schedules to meet the demand. Due to this, Delaware does have a flexible schedule, a lot of these crews are working multiple jobs at once, and the team of managers, supervisors, etc. go by all of the jobs in the area and ensure the quality of the craftsmanship, as well as that they are adhering to our agreed upon schedule. The job is moving along as it should be.
*The 3rd party company will inspect billing and arrival of supplies on Monday.

02/20/2020
Message from the field superintendent: "After this weekend we will have the majority of demo complete and ready for installation of the Jack, piping,  controller,  and conduit.  We plan to delivery new jack, controller , sling " car frame " ,  platform,  all associated piping next week and ready for install. " The field superintendent plans to send an update every 2 weeks.

02/19/2020
All demolition for the K elevator should be wrapped up by this Saturday, and Delaware Elevator should start installing new equipment promptly. The superintendent and project manager are Jose Carrasco and Clayton Bennett.  Please contact resident manager Gene Brewis for any concerns.

02/15/2020
K building elevator demolition began yesterday. Workers were on-site yesterday and today. Harbour Island will not need to pay for the monthly maintenance agreement during construction and will have a year of no charge maintenance inspections when the elevator project is completed for K building. 
 

02/12/2020
Delaware Elevator contacted the condo board today to say that an elevator crew became available to begin our K building project on February 14 if Harbour Island is willing to agree to a last minute start date. Harbour Island jumped at the chance which means that owners received a last minute start date notice. Demolition begins for the K building elevator cab on Friday, February 14th. Yes, it will be inconvenient for K building owners. However, the condo board hopes that the K building owners will appreciate the new cab that has been selected for their building.

01/20/2020
ELEVATOR NEWS: Contracts have been signed and the deposit paid to Delaware Elevator to modernize the K elevator and to replace the sills, sill angles, sill angle brackets, door hardware, and door gibs in L and M elevators. K will receive a new cab to replace the rusting cab. Parts have been ordered for all three elevator jobs. 
K building owners will be notified as soon as parts arrive and it is time to shut down the elevator. The project is being supervised by a 3rd party elevator company (Liberty Elevator) with assistance from Mann Properties.


                     f9ff67dabdbded29470100ccf285b3a8.jpg

This website is operated by the Harbour Island Condo Association. Harbour Island owners are invited to register with this website to gain access to additional website resources. Renters and guests may use the resources listed to the right to enhance their visit. The Harbour Island website and e-mail address are not used for the rental or sale of units or boat slips.
                           
                            [email protected]


Physical Location: Harbour Island • 14th Street & The Bay • Ocean City, MD 21842  
Mailing Address: Harbour Island • P.O. Box 604 • Ocean City, MD 21843